e|agenda.NET
Sarasota County Schools
THE SCHOOL BOARD OF SARASOTA COUNTY, FLORIDA Landings Administrative Complex 1980 Landings Blvd. 3:00 P. M.
July 22, 2008 Board Meeting
Agenda Item #76


Title
ACCEPTANCE OF SUBSTANTIAL COMPLETION FOR THE GULF GATE ELEMENTARY SCHOOL CAMPUS IMPROVEMENTS PROJECT

Description
The architect has prepared the Certificate of Substantial Completion and the final punch list.  The project is substantially complete in accordance with the contract documents.

Recommendation
That the work performed by Willis A. Smith Construction, Inc. for the Gulf Gate Elementary School Campus Improvements project be accepted as substantially complete as of 6/16/2008.

Contact
LEMPE & DUMAS

Financial Impact
N/A


Attachment:  BAIenc7-22-08GulfGateCampusImprvmntsSC-FSD.pdf